Residents fight to protect endangered Blanding’s turtles as unwanted construction of industrial wind proceeds with the invasion of Amherst Island. Ontario meanwhile fails to enforce its own rules and ruling of the Environmental Review Tribunal.
[325] Additionally, the Tribunal finds that the mitigation measures incorporated as conditions of the REA have all but eliminated the potential for turtle mortality and have minimized the potential for indirect impacts to habitat during the construction phase. The construction window of November 1 to March 31 for those portions of the Project closest to the coastal wetlands, and the window of September 1 to March 31 for the remainder of the Project, will ensure that construction takes place outside the period during which turtles are active outside of their resident wetlands.
Extraction from ERT Ruling:15-068 HIRSCH V. ONTARIO (MOECC)
Global News April 25, 2018:
https://globalnews.ca/video/embed/4168160/