“As the community proved at the ERT hearing, this project should not have been approved in the first place,” he said. “It’s outrageous the government could be so negligent, making it necessary for the citizens to protect the public, then hide behind flawed legislation that robs the tribunal appointed by them in overlooking their bad decisions to award costs to the citizens who successfully proved the government compromised people’s safety.”

ERT rules no cost relief to challenge Clearview wind turbine decision
By Ian Adams|Wasaga Sun | Feb 27, 2018
Local taxpayers will be on the hook for the successful challenge to a plan to erect eight turbines in Clearview Township.
The same goes for Kevin and Gail Elwood, John Wiggins, and the residents’ group Preserve Clearview, after the Environmental Review Tribunal dismissed an application for costs related to their appeal of a decision to grant WPD a renewable energy application for the Fairview Wind Project.
The tribunal ultimately ruled last August to revoke that approval on the basis the planned 500-foot-tall turbines presented a serious risk to human health because of the proximity of the project to the Collingwood Regional Airport and the Clearview Aerodrome owned by the Elwoods.