Enforcement Notices Served on Wind project in UK

Armistead-wind-farm-credit-BanksSneddon Law Windfarm – Stop and Enforcement Notices Served

Please be advised that East Ayrshire Council has, as of Wednesday 9 August 2017, served Stop and Enforcement Notices on Community Windpower, and other interested parties, in relation to the works which have been undertaken on site to date and the non-compliance with Condition 36 of planning approval 13/0198/PP (Private Water Supplies)

The notices, in tandem, have the effect on stopping all works associated with the windfarm development until such times as their terms are complied with. The Stop Notice has taken effect immediately and will stay in place until such times as the enforcement notice takes effect on 8 September 2017.

I can confirm that the site has been visited both yesterday and today by officers and Natural Power have been stood down. No works are currently underway and one rig has been removed from site.

It is anticipated that officers from The Council will meet with representatives of Community Windpower to discuss matters and explore possible solutions to the current position at the early part of next week.

I will issue an update following this meeting should any of the current circumstances change significantly.

Best Regards

Tom Dickie
Planning Enforcement Officer

Planning and Economic Development

East Ayrshire Council

The Johnnie Walker Bond

15 Strand Street

Kilmarnock

KA1 1HU

Sneddon Wind Project Details

A New Enemy To Unite Us

The common enemy of humanity is man.
In searching for a new enemy to unite us, we came up
with the idea that pollution, the threat of global warming,
water shortages, famine and the like would fit the bill. All these
dangers are caused by human intervention, and it is only through
changed attitudes and behaviour that they can be overcome.
The real enemy then, is humanity itself
.
– Club of Rome; The First Global Revolution (page75)–

 

 

Water Wells rejecting statement from wind developers north of Chatham as false

Wind Project Manager Calls Water ‘Visually Clear’

A North Kent Wind Project manager referred to a family’s water as “visually clear” in a press release, despite tests and photos that show otherwise.

Brooks family water sample. August 7, 2017. (Photo courtesy of Kevin Jakubec).
Brooks family water sample. August 7, 2017. (Photo courtesy of Kevin Jakubec).

Aecom, the engineering consultant behind the wind project, scheduled a site visit to sample the family’s water on Wednesday. According to Law, the tests show no issues.Senior Manager of Development Jody Law says the Ministry of Environment (MOE) notified him of Paul and Jessica Brooks’ complaint on Monday. Paul and Jessica Brooks live on Brook Line in North Kent and say they have been experiencing a plugged water pump from nearby wind tower pile driving.

“The sample was visually clear and colorless with no visible sediment. We have requested expedited analysis from the lab but, at this point, there is no empirical evidence of an issue,” says Law.

However, Water Wells First spokesperson Kevin Jakubec points out that a Ministry of Environment provincial officer made a visit to the home on Tuesday and found drastically different results.

According to Jakubec, the test results from the MOE show extremely high turbidity levels at 86.8 NTU. The Ontario Drinking Water Standard’s objective turbidity level is 5.0 NTU.

To meet conditions of the wind project’s permit, Pattern Development delivered a 2,000 gallon water tank from Ingersoll to the Brooks residence on Saturday.

“He said that there is no empirical evidence of an issue. I think the delivery of a water tank is recognition of an issue. Given that Mr. Law is the project manager, you’d hope he would know what is going on with this project,” says Jakubec.

Water tank provided to Brooks family by Pattern Development. August 7, 2017. (Photo courtesy of Kevin Jakubec).
Water tank provided to Brooks family by Pattern Development. August 7, 2017. (Photo courtesy of Kevin Jakubec).

Paul and Jessica Brooks demand that North Kent Wind executive Jody Law issues a full apology and retraction of his press release.Jakubec adds the project permit ensures that families, like the Brooks, who complain that their well has been affected by the turbines, do not have to pay for the costs of the investigation or water tanks……

READ ARTICLE: Blackburn News August 8, 2017

 

Well goes bad after pile driving

Pile driving for turbine foundation installations are again being associated to changes in a water well. Another day and another well impacted…

water glass.png

Sediment so thick it prevents water from coming through taps of Chatham Township family’s home

By Ellwood Shreve, Chatham Daily News

Less than two days after pile driving began to construct industrial turbines near Jessica and Paul Brooks’ home in Chatham Township, their once crystal-clear water well has become clogged with sediments.

The couple, who live on Brook Line north of Chatham within the North Kent Wind project area, say the sediment plugs up their system so badly that the water actually stops coming out of the taps at times.

Jessica Brooks said the first sign of the problem occurred last Friday night after 10 p.m. when her husband couldn’t finish taking a shower after work, because the four sediment traps they have installed on their well system were plugged up, preventing the water from flowing through.

They decided to deal with it Saturday morning and found they needed to clean the sediment traps every six hours. A few days later, the sediment traps began clogging at a much faster rate.

Brooks said they called the Ministry of Environment and Climate Control and an official came out on Tuesday.

“They took a sample of water but they did not take the sediments that we had collected over the weekend,” she said.

The Chatham Daily News contacted the MOECC and received a response by e-mail.

“The ministry believes the measurement of turbidity is a key test of water quality in these circumstances because it captures the potential impact on a water well, rather than test for the presence of shale particles alone.

The ministry added samples collected on Tuesday will include analysis for turbidity.

Water Wells First spokesman Kevin Jakubec said the Brooks family has spent upwards of $4,000 on baseline testing recommended by Water Wells First.

Brooks said prior to this issue occurring their water was “beautifully crystal clear.”

She said they have documented tests done in February, March, April, May and June and “it’s all coming back – we have a beautiful well.”

She noted there’s some sodium in the water and it is a little hard, which is common for ground water, but “otherwise it’s a perfect well.”

Brooks said not having drinking water is the least of her concerns, noting they have three teenagers in a home where they can’t take showers, flush the toilet or do laundry.

Jakubec said this is the second well in the North Kent Wind project area that has experienced problems after pile driving activity has taken place nearby.

“Only a fool would think that there’s not a link between pile driving vibrations and impacts on our water wells,” he said…

READ REST of article