Nova Scotia Power Inc.
Grand Etang wind turbine removal gets underway
June 12, 2017Nova Scotia Power is undertaking site cleanup and removal of the Grand Etang wind turbine, which is expected to be completed within the next two weeks.
The turbine has not been in operation since early January following an unexpected collapse of the turbine structure. No one was onsite at the time of the incident and there we no injuries.
A detailed investigation into the turbine collapse has been underway over the past few months, with further analysis of the data and equipment required before the cause of the incident can be confirmed.
Crews have been on-site cleaning up debris from the property and mobilizing a crane that will lift the wind turbine and tower components onto flatbeds for transport. It’s expected that site cleanup and removal of the turbine will be completed within the next two weeks.
Constructed in 2002, Grand Etang was one of the first wind installations in Nova Scotia, with a single 660 kilowatt Vestas V47 wind turbine. That particular turbine model is not used at any other site in the province, either by Nova Scotia Power or independent wind producers.
Nova Scotia Power purchases electricity produced from over 300 public and privately-owned wind turbines in operation across the province.
For more information:
Organization: Nova Scotia Power Inc.Address: PO Box 910 Halifax, Alberta Canada, B3J 2W5 www.nspower.ca Tel: 902-428-6230 |
Source: Nova Scotia Power Inc.

“If it’s too windy, then maybe it’s not the right place for it,” said Aucoin. “Because it is close to houses and I imagine the people up the hill … they must have been scared because it was right near to their house.”
Laurette Chiasson, a resident who has lived in the area for 59 years, said she’s never had a problem with the windmill, though she was scared after the collapse about pieces hitting the house.
CBC article January 5, 2017: People near snapped wind turbine say winds were high but not unprecedented